Decision details

Assessment Under The Habitat Regulations: Old Moor Quarry, Wormhill

Decision status: APPROVED (In accordance with officer recommendation)

Is Key decision?: No

Is subject to call in?: No

Decisions:

The Director of Planning stated that this item had been brought to the Committee as it was a technical assessment that the Authority was required to complete and that a report on the ROMP determination would be brought to the Committee next month.

 

The recommendation as set out in the report was moved, seconded, voted on and carried.

 

RESOLVED:

 

That the report, including annex 1, be adopted as the Authority’s Habitat Regulations Assessment in relation to the determination of modern working conditions under the Review of Old Mineral Permissions process at Old Moor Quarry.

 

It is determined that continued Mineral Working is unlikely to have a significant effect on the integrity of the Peak District Dales SAC. Thus continued quarrying is not considered to be contrary to the provisions of Regulation 61 of the Conservation of Habitats and Species Regulations 2010 and the EU Habitats Directive and an Appropriate Assessment is not considered necessary.

 

 

Publication date: 04/11/2015

Date of decision: 09/10/2015

Decided at meeting: 09/10/2015 - Planning Committee

Accompanying Documents: