Full Application - Replace existing cess pitt with sewage treatment plant. New treatment plant to be within existing site boundary but at a new position. Installation of new drainage pipes and inspection chambers to connect sewage treatment plant to
Decision Maker: Planning Committee
Decision status: APPROVED (In accordance with officer recommendation)
Is Key decision?: No
Is subject to call in?: No
Decisions:
Reason for Urgency: This development is business critical for the applicant.
This was an application by the Authority. It was noted that contractors were already on site carrying out other work and would like to be able to continue working.
The following person had submitted a comment on the report:
· Mr K Smith, Authority Member
The comment made supporting the application was noted.
RESOLVED:
That the application be APPROVED subject to the following conditions:
1. Standard 3 Year time limit
2. Submitted plans and details
Publication date: 23/04/2020
Date of decision: 03/04/2020
Decided at meeting: 03/04/2020 - Planning Committee