Agenda item

Full Application - Conversion of Barn to Holiday Accommodation at Barn at Carr Lane, Wetton

Minutes:

It was noted that Members had visited the site on the previous day.

 

The following spoke under the public participation at meetings scheme:

 

·         Cllr M Goodridge, Chair of Wetton Parish Council, Objector

·         Mr P Atkinson, Applicant.

 

In response to Members’ queries officers stated that the Highway Authority had been consulted but had not raised any issues and that although the structural appraisal didn’t specifically refer to the foundations of the barn it did state the walls can support rebuilding.

 

The recommendation for approval subject to conditions was moved and seconded.  It was agreed to include additional conditions to limit permitted development,  including for external lighting, the dry stone wall to be extended round the car parking area and access tracks, existing wall materials to be reused and approval of gate details.  The motion was then voted on and carried.

 

RESOLVED:

 

That the application be APPROVED subject to the following conditions:

 

1.    3 year implementation period.

 

2.    Development to be carried out in accordance with specified amended plans.

 

3.    Rebuilding limited to that specified in the submitted structural report.

 

4.    Holiday occupancy restriction.

 

5.    Extent of use limited to the building itself and the parking bay, with the remainder of the field excluded.

 

6.    Conditions securing the proposed protected species mitigation measures (excluding the proposed hedgerow), and the additional measures recommended by the Authority’s ecologist.

 

7.    All new stonework to match the existing with the dry stone wall being extended around the car parking area.

 

8.    Sample of roof material to be approved.

 

9.    Conditions securing architectural design details.

 

10.  All services to be undergrounded.

 

11.  Details of foul water disposal to be approved.

 

12.  Details of surfacing to parking bay to be approved.

 

13.  Design and appearance of new gates to be approved.

 

14.  Parking to be provided prior to the approved use commencing.

 

15.  Scheme of archaeological recording and monitoring to be approved.

 

16.  Removal of permitted development rights.

 

17.  Existing wall materials to be reused.

 

18.  Details of gate to be approved.

 

Supporting documents: