Agenda item

S73 Application - Removal of Condition 10 ON NP/DDD/0613/0542 and modification of S106 Legal Agreement under S106A to remove clauses 2 and 3 of the second schedule at Quarters Farm, Buxo Plas Manufacturing Ltd, Quarters Lane, Hazlebadge

Minutes:

 

 

This item was considered in conjunction with Item 6, details of which are in the minute138/19.

 

The speaker on Item 6 was asked if they wished to make any further comments with regard to this Item.

 

Ms Lizzie Marrjoram, Legal Representative on behalf of the Agent, provided an update regarding the landscaping concern that had been raised, and confirmed that further submissions were to be to made in respect of landscaping, and that they had already been engaging with Officers.

 

The Officer recommendation to approve the application subject to amending Conditions 10 & 5 was moved, seconded, put to the vote and carried.

 

 

RESOLVED:

 

1.            A. That the application be APPROVED subject to the following conditions and/or modifications and,

2.            B. That the S106 be varied to remove clauses 2 and 3 of schedule 2.

 

1.

The  development  hereby  approved  shall  not  be  carried  out  otherwise  than  in  complete accordance  with  the  submitted  plans  and  specifications  numbered  1314-01  Rev  A  Proposed elevations; 1314-02 Rev A Proposed Block Plan; 1314-05 Existing & Proposed Floor Plan; and the amended drawings numbered Amended Site Plan and Amended Location Plan which were received by this office on 19  July 2013 subject to the following conditions and/or modifications:-

 

2.

The building and its extension shall be used solely for purposes relating to the development, production and storage of extruded plastic tubing and for no other purposes. Notwithstanding the provisions of The Town and Country Planning (General Permitted Development) (England) Order 2015 (or any Order revoking and re-enacting that Order with or without modification), the use shall be limited to that specified in this condition and for no other purposes.

 

3.

The sheeting for the doors, walls and roof of the extension shall be factory colour-coated to BS 5252 Ref. No. 12 B 29 (dark green) and thereafter the sheets shall not be repainted or replaced  other than that colour without the prior written approval of the National Park Authority.

 

4.

All  external  timberwork  shall  be  stained  dark  brown  or  black  and  shall  be permanently  so  maintained.

 

5.

The dry limestone render on the block walls shall be maintained as a rendered finish.

 

6.

There shall be no external storage of materials or goods in connection with the development hereby permitted.

 

7.

Notwithstanding the  details  shown  on the  approved  plans a  detailed  scheme  for landscaping  (including tree planting,  drystone and retaining walling and any structures which shall be faced  in rubble limestone as necessary) shall be submitted to and approved in writing by the National Park Authority within 2 months of the date of this permission being granted. Once approved, the planting or seeding shall be carried out to the reasonable satisfaction of the Authority within the  first  planting  seasons  following  completion  or  occupation  of  the  extension.  Any  trees  dying,  being  severely  damaged  or  becoming  seriously  diseased  shall  be  replaced  within  the  next planting  season  with  trees  of  an  equivalent  size  and  species  or  in  accordance  with  an alternative scheme agreed in writing by the Authority before any trees are removed.

 

8.

Prior to the disposal of any spoil arising from the works, precise details of the disposal shall be  submitted  to  and  approved  in  writing  by  the  National  Park  Authority.   All spoil shall then be disposed of in accordance with the approved details.

 

9.

The use  hereby permitted  shall only be conducted between  6am and 8pm on weekdays and 8am and 6pm on Saturdays and at no time at all on Sundays, Bank or Public Holidays.

 

10.

To submit a scheme for external lighting within 3 months of the date of this permission being granted to be approved  in  writing  by  the  National  Park  Authority. The development shall then be carried out in accordance with the approved details and permanently so maintained.

 

 

 