It was noted that Members had visited the site on the
previous day.
The officer used a PowerPoint presentation to show the
location and extent of each of the three phases of the proposed extension.
He reported that following the hay meadow translocation appraisal,
there had been agreement with the applicant that the complete translocation of
hay meadow identified during Phase 1B would not take place. It was proposed to
translocate the hay meadow from the Phase 1 and Phase 2 areas, but if this
proved unsuccessful, the translocation of hay meadow and mineral working from
the remaining Phase 3 area would not take place.
The following amendments to the report were noted:
·
Page 4 condition 10 – after “revised
information” add “following agreement of the hay meadow translocation
methodology, no hay meadow translocation and no tipping of quarry waste in Tip
T2 shall take place if the translocation of the hay meadow under Phase 1 and
the Phase 2 working area has failed. If successful, then hay meadow translocation
and mineral working will take place in the next Phase, but there shall be no
storage of waste in Tip T2.”
·
Page 4 condition 7 – after “no more than 750
tonnes per annum” add “or 30%, whichever is the greater”
·
Page 5 condition 31 Site and Quarry access and transportation
– amend to state “no more than 5 lorry movements in and 5 out of the site per
day.”
·
Page 17 paragraph 8 and page 27 paragraph 2 –
delete reference to “unilateral”
·
Page 25 paragraph 6 – add “area” between “wider”
and “which”
The following spoke under the Authority’s Public Participation Scheme:
·
Cllr Mrs K Potter, Authority Member and Chair of
Rowsley Parish Council
After speaking, Cllr Mrs Potter left the room and took no
part in the debate or voting.
The recommendation of approval including the amended
conditions was moved, seconded, put to the vote and carried.
RESOLVED:
|
It
is recommended that, subject to the prior completion of the S106 planning
obligation whereby the Applicant, and those with an interest in the site,
formally agree to:
(a)
the use of the
extraction stone solely for dimensional stone purposes, and
(b)
No more than 750 tonnes per annum, or 30%, whichever is the greater in
total (calculated January to December) of stone product shall be removed from
the site where delivery addresses are outside the Peak District National Park.
|
|
A) That the
application be APPROVED subject to conditions covering the following:
- Development
to commence within 3 years from the date of the permission.
- Duration
for the winning and working of mineral to 30 September 2042, the removal
of buildings and restoration completed by 30 September 2043.
- The site
and approved details - development to be undertaken in accordance with
the application details.
- Type of Mineral - No mineral other
than limestone to be extracted from the site shall be worked.
- Output
Restriction - Limestone shall only be removed from the site for
building, walling and decorative stone uses.
- Mineral
Restriction - Limestone shall not be removed from the site as or in the
form of aggregate.
- Destination
Restriction - No more than 750 tonnes per annum, or 30%, whichever is
the greater in total (calculated January to December) of stone product
shall be removed from the site where delivery addresses are outside the
Peak District National Park boundary.
- Right to
Inspect Delivery Notes.
- Submission
of a statement of sales.
- Working
scheme including phasing – development to be undertaken in accordance
with the 3 phases of working identified in the application and revised
information following agreement of the hay meadow translocation
methodology, no hay meadow translocation and no tipping of quarry waste
in Tip T2 shall take place if the translocation of the hay meadow under
Phase 1 and the Phase 2 working area has failed. If successful, then hay
meadow translocation and mineral working will take place in the next
Phase, but there shall be no storage of waste in Tip T2.
- Submission
and approval of Hay meadow Translocation methodology prior to
commencement), including measures of translocation success.
- Phase 3
quarry operations shall not proceed should Phase 1 & 2 be deemed
unsuccessful.
- 10 year
aftercare period for Translocation Phase 1 and 2.
- Translocation works supervision - Preparation of donor and
receptor sites, aftercare and management shall be supervised by a
competent and suitably experienced Ecologist.
- Aftercare of all translocated turf
shall begin immediately after Phase 1 & 2 have been moved to the
receptor site, and shall continue for a period of at least 10 years
after turves from phase 3 have been placed on the receptor site
- Fencing –
submission of fencing details prior to commencement.
- Method
statement for Great Crested Newts mitigation – to be submitted for
approval prior to commencement).
- Agreement
of access route for the internal haul road – access route set out in the
details and plan submitted in the application (pre-commencement)
- Restoration
– implication of restoration plan as set out in the restoration
management plan.
- Site
Access – Use of approved vehicle access.
- Access improvements – Submission of a
scheme of junction improvements (pre-commencement).
- Submission
and implementation of landscaping scheme for quarry.
- Biodiversity
and habitat creation - submission and approval of details.
- Pond -
Retention of pond and surrounding habitat within the site. - Management
and control of Canadian pondweed.
- Restoration,
aftercare and management of quarry – Submission of restoration and
aftercare proposals and 5 year aftercare period.
- Recreational
access provision to be agreed.
- Production of appropriate information
and interpretation.
- Details of
drystone walling repair to be agreed.
- Hours of
working – 07:30 - 17:30 daily Monday to Friday, 07:30 - 12:00 Saturday;
no working on Sundays, Bank or Public Holidays: except for emergency
operations
- Output and
resource monitoring- no more than 2,500 tonnes to be removed from the
site per annum; total extracted stone leaving the site shall not exceed
69,000 tonnes; provision of annual output records to Authority in
January of each year
- Site and
Quarry access and transportation – no more than 5 lorry movements
in and 5 out of the site per day carrying stone from the site; via the internal haul road onto
Flagg Lane; lorry types.
- Quarry
waste control - any overburden shall be used within the site for
progressive restoration.
- Archaeology - erection of protective fencing
to protect remnant industrial features; a programme of archaeological work including a Written Scheme of
Investigation to be submitted for approval (pre-commencement).
- Noise -
noise levels from site operations shall not exceed 10dB Laeq1h above
background noise levels or where the background noise is below 35 Laeq1h
shall not exceed a limit of 45 Laeq1h.
- Blasting -
no blasting permitted.
- Dust,
Smoke and Fumes – make available facilities to include water bowser, to
control dust problems arising.
- Lighting -
no lighting without Authority’s consent.
- Drainage
and water pollution – prevention of slurry, no discharge of foul or
contaminated drainage from the site; suitable storage of oils fuel or
chemicals; no vehicle maintenance except on impermeable areas.
- Restrict
permitted development rights (buildings, structures, plant machinery)
colours of ancillary buildings; parking of plant and vehicles; and
removal of ancillary development when no longer required.
|
B. That authority be delegated to the
Director of Planning and the Head of Law jointly to determine the details of
the section 106 obligation.
C. That authority is delegated to the
Director of Planning to approve the final details of the conditions in
consultation with the Chair and Vice Chair of the Planning Committee.