It was noted that Members had visited the site
on the previous day.
The officer used a PowerPoint presentation to
show the location and extent of each of the three phases of the
proposed extension.
He reported that following the hay meadow
translocation appraisal, there had been agreement with the
applicant that the complete translocation of hay meadow identified
during Phase 1B would not take place. It was proposed to
translocate the hay meadow from the Phase 1 and Phase 2 areas, but
if this proved unsuccessful, the translocation of hay meadow and
mineral working from the remaining Phase 3 area would not take
place.
The following amendments to the report were
noted:
·
Page 4 condition 10 – after “revised information”
add “following agreement of the hay meadow translocation
methodology, no hay meadow translocation and no tipping of quarry
waste in Tip T2 shall take place if the translocation of the hay
meadow under Phase 1 and the Phase 2 working area has failed. If
successful, then hay meadow translocation and mineral working will
take place in the next Phase, but there shall be no storage of
waste in Tip T2.”
·
Page 4 condition 7 – after “no more than 750 tonnes per
annum” add “or 30%, whichever is the greater”
·
Page 5 condition 31 Site and Quarry access and transportation
– amend to state “no more than 5 lorry movements in and
5 out of the site per day.”
·
Page 17 paragraph 8 and page 27 paragraph 2 – delete
reference to “unilateral”
·
Page 25 paragraph 6 – add “area” between
“wider” and “which”
The following spoke under the
Authority’s Public Participation Scheme:
·
Cllr Mrs K Potter, Authority Member and Chair of Rowsley Parish Council
After speaking, Cllr Mrs Potter left the room
and took no part in the debate or voting.
The recommendation of approval including the
amended conditions was moved, seconded, put to the vote and
carried.
RESOLVED:
RECOMMENDATION
It is
recommended that, subject to the prior completion of the S106
planning obligation whereby the Applicant, and those with an
interest in the site, formally agree to:
(a)
the use of the extraction stone solely
for dimensional stone purposes, and
(b)
No more than 750 tonnes per annum, or
30%, whichever is the greater in total (calculated January to
December) of stone product shall be removed from the site where
delivery addresses are outside the Peak District
National Park.
|
A) That the application be APPROVED subject to
conditions covering the
following:
- Development to commence within 3 years from the
date of the permission.
- Duration for the winning and working of mineral
to 30 September 2042, the removal of buildings and restoration
completed by 30 September 2043.
- The site and approved details - development to be
undertaken in accordance with the application
details.
- Type of Mineral - No mineral other than limestone
to be extracted from the site shall be worked.
- Output Restriction - Limestone shall only be
removed from the site for building, walling and decorative stone
uses.
- Mineral Restriction - Limestone shall not be
removed from the site as or in the form of
aggregate.
- Destination Restriction - No more than 750 tonnes
per annum, or 30%, whichever is the greater in total (calculated
January to December) of stone product shall be removed from the
site where delivery addresses are outside the Peak District
National Park boundary.
- Right to Inspect Delivery Notes.
- Submission of a statement of
sales.
- Working scheme including phasing –
development to be undertaken in accordance with the 3 phases of
working identified in the application and revised
information following agreement of the hay meadow
translocation methodology, no hay meadow translocation and no
tipping of quarry waste in Tip T2 shall take place if the
translocation of the hay meadow under Phase 1 and the Phase 2
working area has failed. If successful, then hay meadow
translocation and mineral working will take place in the next
Phase, but there shall be no storage of waste in Tip T2.
- Submission and approval of Hay meadow
Translocation methodology prior to commencement), including
measures of translocation success.
- Phase 3 quarry operations shall not proceed
should Phase 1 & 2 be deemed unsuccessful.
- 10 year aftercare period for Translocation Phase
1 and 2.
- Translocation works supervision - Preparation of donor and
receptor sites, aftercare and management shall be supervised by a
competent and suitably experienced Ecologist.
- Aftercare of all translocated turf
shall begin immediately after Phase 1 & 2 have been moved to
the receptor site, and shall continue for a period of at least 10
years after turves from phase 3 have been placed on the receptor
site
- Fencing – submission of fencing details
prior to commencement.
- Method statement for Great Crested Newts
mitigation – to be submitted for approval prior to
commencement).
- Agreement of access route for the internal haul
road – access route set out in the details and plan submitted
in the application (pre-commencement)
- Restoration – implication of restoration
plan as set out in the restoration management plan.
- Site Access – Use of approved vehicle
access.
- Access improvements – Submission of a
scheme of junction improvements (pre-commencement).
- Submission and implementation of landscaping
scheme for quarry.
- Biodiversity and habitat creation - submission
and approval of details.
- Pond - Retention of pond and surrounding habitat
within the site. - Management and
control of Canadian pondweed.
- Restoration, aftercare and management of quarry
– Submission of restoration and aftercare proposals and 5
year aftercare period.
- Recreational access provision to be
agreed.
- Production of appropriate information
and interpretation.
- Details of drystone
walling repair to be agreed.
- Hours of working – 07:30 - 17:30 daily
Monday to Friday, 07:30 - 12:00 Saturday; no working on Sundays,
Bank or Public Holidays: except for emergency
operations
- Output and resource monitoring- no more than
2,500 tonnes to be removed from the site per annum; total extracted
stone leaving the site shall not exceed 69,000 tonnes; provision of
annual output records to Authority in January of each
year
- Site and Quarry access and transportation
– no more than 5 lorry movements in and 5 out of the
site per day carrying stone from the
site; via the internal haul road onto Flagg Lane; lorry
types.
- Quarry waste control - any overburden shall be
used within the site for progressive restoration.
- Archaeology - erection of protective
fencing to protect remnant industrial features; a
programme of archaeological work including a Written Scheme of
Investigation to be submitted for approval
(pre-commencement).
- Noise - noise levels from site operations shall
not exceed 10dB Laeq1h above background noise levels or where the
background noise is below 35 Laeq1h shall not exceed a limit of 45
Laeq1h.
- Blasting - no blasting permitted.
- Dust, Smoke and Fumes – make available
facilities to include water bowser, to control dust problems
arising.
- Lighting - no lighting without Authority’s
consent.
- Drainage and water pollution – prevention
of slurry, no discharge of foul or contaminated drainage from the
site; suitable storage of oils fuel or chemicals; no vehicle
maintenance except on impermeable areas.
- Restrict permitted development rights (buildings,
structures, plant machinery) colours of ancillary buildings;
parking of plant and vehicles; and removal of ancillary development
when no longer required.
|
B. That authority be delegated to the Director of
Planning and the Head of Law jointly to determine the details of
the section 106 obligation.
C. That authority is delegated to the Director of
Planning to approve the final details of the conditions in
consultation with the Chair and Vice Chair of the Planning
Committee.