Agenda item
Conservation of Habitats and Species Regulations 2017 - Essential safety works to reservoir dam including removing the auxiliary spillway, replacement of the primary spillway and works to existing wave wall, legally required as measures in the interest of safety under the reservoirs act at Swellands Reservoir off the A62 Huddersfield Road, Diggle, Saddleworth (NP/K/0322/0346, JK)
Minutes:
Item 5 was dealt with at the same time as Item 6 but the votes were taken separately. Please see full minute in detail in minute 48/22.
A motion to approve the recommendation, was moved and seconded, and a vote was taken and carried.
RESOLVED:
1. That this report be adopted as the Authority’s assessment of likely significant effects on internationally important protected habitats and species under Regulation 63 of the Conservation of Habitats and Species Regulations 2017 (as amended) in relation to the proposal for the carrying out of essential safety works to Swellands reservoir dam, including removing the auxiliary spillway, replacement of the primary spillway and works to existing wave wall.
Supporting documents:
- 0322-0346. Essential Safety Works to Swellands Reservoir HRA report. May 2022.v1, item 47/22 PDF 330 KB
- Item 5 & 6 - Swellands Reservoir, Diggle, item 47/22 PDF 526 KB