Agenda item

Listed Building Consent - Repair and conversion of barns into two c3 dwellings / holiday lets at Green Farm, Church Barns, Weaddow Lane, Middleton by Youlgrave, (NP/DDD/1123/1336/PM)

Minutes:

Item 10 was presented and discussed at the same time as Item 9, but the votes were taken separately.    Please see the full minute details 42/24 above.

 

A motion to approve the application was proposed, and seconded, put to the vote and carried subject to additional conditions regarding, shutters, specification for the solar panels and lighting.

 

RESOLVED:

 

That the application is APPROVED subject to the following conditions and the additional conditions outlined by the Planning Officer:    

 

1.            Standard time limit

 

2.            Carry out in accordance with specified approved plans and documents

 

3.            No works shall take place until a Written Scheme of Investigation for a scheme of a programme of level 3 building recording has been submitted to and approved in writing by the National Park Authority.

 

4.            A methodology including proposed mortar mix and finish for any rebuilding of the existing elevations to be submitted and approved in writing by the National Park Authority.  Once approved, a sample panel of rebuilt wall shall be made available for inspection on site.

 

5.            A methodology including mortar mix for any repointing to the existing stonework to be submitted to and approved in writing by the National Park Authority.

 

6.            Precise details of proposed insulation to roofs, floors and walls of buildings to be submitted to and approved in writing by the National Park Authority.

 

7.            A methodology for lifting, recording and relaying of stone floors to be submitted to and approved in writing by the National Park Authority. 

 

8.            Precise details of windows, doors and shutters including design, material, finish and colour to be submitted to and approved in writing by the National Park Authority.

 

9.            Details of new rainwater goods to be submitted to and approved in writing by the National Park Authority.

 

10.          Details of any new external vents to be submitted to and approved in writing by the National Park Authority.

 

11.          All pipework, other than rainwater goods, shall be completely internal within the building.

 

12.          Mitigation and compensation enhancements presented within the bat and bird survey report to be implemented in full. 

 

13.          Provision of a bird compensation and enhancement strategy for barn swallow to be submitted to and approved in writing by the National Park Authority. 

 

14.          Pre-works bird nest checks shall be carried out on the barn by a suitably qualified ecologist prior to any works taking place within the bird breeding season (March to August inclusive). If active bird nests are present works must cease until chicks have fledged the nest.

 

15.          The air source heat pumps shall not be installed other than in complete accordance with a detailed scheme which shall have first been submitted to and approved in writing by the National Park Authority.

 

Supporting documents: