Agenda item

Policy Referral for Full Application - Proposed siting of 24 static holiday caravans with additional landscaping in lieu of 28 touring caravans and two tented camping areas at Newhaven Holiday Park, Newhaven (NP/DDD/1024/1137, AM)

Minutes:

The Policy & Communities Officer presented the report and reminded Members that the application had been referred back to the April Planning Committee, due to Members being minded to approve the original application on the 14th March, which would have been a departure from Policy RT3B of the Core Strategy.

 

The Officer informed Members that the risk was low so the application was not considered to be a major departure from the Development Plan, due to there being exceptional reasons for approval in this case.

 

Members reminded the Planning Officer  that the provision of EV Charging Points be added to the list of conditions as this was omitted from the original  list of conditions.

 

A motion to approve the application was moved, seconded, put to the vote and carried.

 

RESOLVED:-

 

That the application be APPROVED subject to the following conditions:

 

1.

Statutory 3 year time limit for implementation

 

2.

In accordance with submitted and amended plans

 

3.

28-day holiday occupancy restriction

 

4.

Colour range of units to be approved and implemented

 

5.

Biodiversity Net Gain plan to be implemented

 

6.

Habitat creation and management plan to be approved and implemented

 

7.

In accordance with the recommendations of the protected species report

 

8.

In accordance with the recommendations of the tree report

 

9.

Programme of monitoring and site supervision of arboricultural measures to be approved

 

10.

Final Tree Protection Plan (TPP) and Arboricultural Method Statement (AMS) to be approved and implemented

 

11.

Planting to be carried out as approved

 

12.

Woodland management plan to be approved and implemented

 

13.

Parking plan to be approved

 

14.

 

 

15.

Travel Plan to be approved if approved parking plan includes provision of more than 28 spaces

 

Installation of EV Charging Points

 

 

 

 