Agenda item

Full Planning Application - The Redevelopment of the Former Brooklands Christian Care Home Site on Coombs Road, and the Creation of 4 Dwelling Houses on the Site at the Brooklands, Coombs Road, Bakewell (NP/DDD/0523/0494) MN

Minutes:

Item 6 was presented and discussed at the same time as item 7 but the votes were taken separately. 

 

Some Members had visited the site the previous day.

 

The Planning Officer presented the report and outlined the reasons for approval subject to resolution of matters of surface water drainage as outlined in the report.

 

The following spoke under the public participation at meetings scheme:

·         Sarah Foster, Agent

 

A motion to approve the application as proposed, delegating authority to officers to issue the decision subject to resolution of drainage matters   and with additional conditions to address the cladding material to plot 4 and to secure secure building recording, tree protection during works and longer term tree retention, was moved, seconded, put to the vote and carried.

 

RESOLVED:

 

That the application be APPROVED subject to the following conditions:

 

That delegated power be granted to the Head of Planning, Development and Enforcement Manager and Area Team Manager to APPROVE the application subject to agreement of drainage matters and relevant conditions with the Lead Local Flood Authority and subject to the following conditions:

 

  1. 3-year time limit

 

  1. In accordance with amended plans and details

 

  1. Phasing of development to secure the conservation works to the principal listed building prior to the commencement of other parts of the development

 

  1. Scheme of archaeological recording and monitoring

 

  1. Scheme of landscaping

 

  1. Implement tree protection measures during construction.

 

  1. Remove permitted development rights for alterations, extensions, outbuildings, and boundaries

 

  1. Conversion of buildings only with no demolition other than shown on plans

 

  1. Design and repair details, to include amongst other things window retention, works to floors, and roof alterations

 

  1. Scheme of external lighting

 

  1. Climate change mitigation measures to be implemented

 

  1. Recommendations of the ecological assessment to be implemented

 

  1. Agree construction compound

 

  1. Provision and maintenance of modified access through lifetime of the development.

 

  1. Retain garages for the parking of domestic vehicles.

 

  1. Materials to first floor cladding of Plot 4 dwelling to be amended
  1. Scheme of tree protection measures to be secured
  1. Existing mature trees to be retained for 5 years

 

 